Building materials: concrete, shingles, decking and lumber
The four units that decide a structural purchase: cubic yards for concrete, bundles for shingles, boards for decking, board feet for lumber. Each one hides a conversion that trips up a first order — bag yield, bundle coverage, row spacing, and the kerf.
Pick the tool
Each one is free, works in imperial or metric, and prints a shopping list you can take to the yard.
Concrete calculator
Slab, footing or column — cubic yards, bags and the pour you should order.
Adds the bag count where ready-mix wins: about 45 bags of 80 lb to one yard Roofing · ShinglesRoof shingle calculator
Bundles, ridge cap, starter strip and underlayment for a gable roof.
Adds ridge cap on its own line, and pitch taking bundles from 41 to 57 Decking · BoardsDeck board calculator
Rows, boards, joists and screws for the surface, plus the gap you will actually set.
Adds what to do when the width will not divide evenly: three fixes, each priced Lumber · Board feetBoard foot calculator
Board feet for your cut list, turned into the number of boards on the rack.
Adds which stock length wastes least: 10 boards at 12 ft, 20 at 8 ft, same lumber Wall · BrickBrick calculator
Bricks, courses and mortar bags with the joint counted as part of the module.
A 3/8 in joint is what turns a 7⅝ in brick into an 8 in moduleEvery unit here has a conversion hidden inside it
Get the conversion wrong and you are short by a whole delivery, not by a rounding error.
Concrete is ordered in cubic yards, but most people buy bags. A 60 lb bag yields about 0.45 cu ft, an 80 lb bag about 0.6 — so the same pour is 82 bags or 62 bags depending on which sack you load. Above about one yard, ready-mix usually wins even after the short-load fee, and the calculator prints both sides.
Shingles are counted in bundles per square — 100 sq ft of roof — and a steep pitch adds roof area without adding floor area. A 6/12 pitch carries a 1.118 factor: a 30 × 20 footprint becomes 1,342 sq ft of actual roof. Decking is counted in rows, and the row count depends on board width plus the gap you set, not on the deck's area. Lumber is counted in board feet, then converted into whole boards, which is where the kerf and the off-cut show up.
| Material | Unit | The hidden conversion |
|---|---|---|
| Concrete | Cubic yards | Bag yield: 0.45 cu ft at 60 lb, 0.6 at 80 lb |
| Shingles | Bundles per square | Pitch factor: 1.000 flat, 1.118 at 6/12, 1.414 at 12/12 |
| Decking | Boards | Rows = width ÷ (board width + gap), not area ÷ board area |
| Lumber | Board feet | Kerf per cut and the off-cut at the end of every board |
None of these tools will size a beam, a footing or a load path. They count material. Structural decisions belong to whoever stamps the drawing.
Related guides
Long-form walkthroughs that go past the formula, with worked examples and the mistakes that cost the most.
Then stack it with the rest of the house
This tool gives you the order for one job. Save it to a project and the same page adds up several rooms, tracks what is still unbought, and records what you actually paid against the estimate.